Explore

Learn: Completing CPA Diagrams
WJEC Eduqas GCE A LEVEL in BUSINESS specification
Ready to start this lesson?
Sign in to track your progress. 17 steps including 8 interactive questions.
Sign In to Start LearningStudents also studied
Browse allSteps in this lesson (17)
Welcome!Great to see you back! You've already explored decision-making tools like decision trees and learned how Critical Path Analysis (CPA) helps businesses optimise tasks. Now, we're going to focus on how to complete CPA diagrams. Ready to dive in?
What is a CPA Diagram?A Critical Path Analysis diagram is a visual representation of tasks in a project, showing their dependencies and duration. It helps businesses identify the sequence of activities and the minimum time required to complete a project.
Key Elements in a CPA DiagramCPA diagrams contain several parts:Nodes: Represent the start and end of activities.Activities: Tasks that need to be completed, shown as arrows between nodes.Earliest Start Time (EST): The earliest time an activity can start.Latest Finish Time (LFT): The latest time an activity can finish without delaying the project.Understanding these elements is crucial for completing CPA diagrams correctly.
What do nodes represent in a CPA diagram?
Start the lesson to answer this multiple choice question
Understanding DependenciesIn CPA diagrams, some tasks cannot start until others are finished. These are called dependencies. Identifying dependencies is critical to finding the longest path (critical path) and the total duration of the project.
An activity depends on the {{blank0}} and {{blank1}} tasks to be completed before it starts.
Start the lesson to answer this fill in the blank question
Calculating EST and LFTThe Earliest Start Time (EST) is calculated by adding the duration of previous tasks along the path. The Latest Finish Time (LFT) is calculated by working backwards from the project's final node.These times help identify the float, which is the amount of time a task can be delayed without affecting the project's overall duration.
Match the items on the left with their correct pairs on the right
Start the lesson to answer this math equation question
What is the Critical Path?The Critical Path is the sequence of tasks that determines the minimum time required to complete a project. It is the longest path in a CPA diagram and has no float, meaning any delay will affect the project’s completion time.
What happens if a task on the critical path is delayed?
Start the lesson to answer this multiple choice question
Reviewing FloatFloat is the amount of time a task can be delayed without affecting the project's completion time. Float is calculated as:Float = LFT - EST - DurationTasks on the critical path have zero float.
Tasks on the {{blank0}} path always have {{blank1}} float.
Start the lesson to answer this fill in the blank question
Review Time!Great work! You've learned about completing CPA diagrams, including nodes, dependencies, EST and LFT, and identifying the critical path. Let’s test your understanding of these key concepts.
Which of the following are true about CPA diagrams? (Select all that apply)
Start the lesson to answer this multi-select question
Match the items on the left with their correct pairs on the right
Start the lesson to answer this matching question
Match the items on the left with their correct pairs on the right
Start the lesson to answer this math equation question
Well Done!You've mastered completing CPA diagrams. Keep practising to build confidence in identifying critical paths, calculating float, and optimising project timelines!

Want to Learn More?
Get personalised lessons, quizzes, and instant feedback from your AI tutor.
Explore More Topics